Heater project

This project consisted of 14 NOS of heater platforms in an industrial building. Main building structures were constructed with structural steel using WF (Beams & Columns), HSS Tubes, Channels, Angles, Plates, and floor handrails & ladders.

 

We detailed the entire structure using TEKLA, including but not limited to heater platform support connection coordination, grating supports, circular platforms, cantilever platforms, and handrails & ladders

 

Steel columns used bolted splice connections, as well as welded splices. Beams were mainly connected with bolts and nuts, using shear and moment connections.

 

Total Tonnage: 2500 Tons

 

Duration: 12 Weeks

 