Westlake project (2021 – 2022)

 This project consisted of 16 floors of commercial building. Main building structures were constructed with structural steel using WF (Beams & Columns), HSS Tubes, Channels, Angles, Plates and Rebar’s profiles.

 

We detailed the entire structure using TEKLA, including but not limited to screen walls, encased columns, stairs and handrails with perforated plates, precast co-ordination, and deck floor co-ordination.

 

Steel columns used bolted splice connections, as well as welded splices.  Beams were mainly connected with bolts and nuts, using side plate connections.

 

Total Tonnage: 2500 Tons

 

Duration: ~12 Weeks