Shepherd Hotel project (2021)

 This project consisted of 6 floors of hotel building. Main building structures were constructed with structural steel using WF (Beams & Columns), HSS Tubes, Channels, Angles and Plates.

 

We detailed the entire structures using TEKLA, including but not limited to elevator divider, beams and roof equipment supports, canopies, screen walls, and deck floor co-ordination.

 

Steel columns used bolted splice connections, as well as welded splices. Beams were mainly connected with bolts and nuts, using shear and moment connections.

 

Total Tonnage: 300 Tons

 

Duration: 4 Weeks